View Full Version : FERC Rules on MISO Queue Reform


Kristy
09-09-2008, 06:10 PM
On August 25, 2008, the Federal Energy Regulatory Commission (the "Commission" or "FERC") conditionally approved the Midwest Independent Transmission System Operator's ("MISO") proposal to reform the generator interconnection queue process. This order is part of an ongoing effort by the Commission and Regional Transmission Operators ("RTOs") and Independent System Operators ("ISOs") to reform the process through which generators/developers interconnect to the transmission system.

More... (http://www.RenewableEnergyWorld.com/rea/news/story?id=53542&src=rss)